Key Activities to take place in terms of the IDP, BUDGET and PMS for the 2015-16 IDP Process

IDP PHASES AND PERFORMANCE REPORTING ACTIVITY DATES FACILITATION
 

PREPARATION PHASE

Briefing session with Section 80: IDP and Finance, MAYCO 13 Aug 2014 CM
Initiate tariffs setting review process & benchmarking (services tariffs to be cost reflective) 20 Aug 2014 CFO
Tabling of the IDP and Budget Process Plan to Council. 28 Aug 2014 DEM
Final submission of Municipal Growth and Development Strategy for the City to the EM 29 Aug 2014 CM
Executive Mayor facilitates the establishment of the Budget Steering Committee 31 Aug 2014 EM/CM
Advertisement of IDP and Budget Process Plan. 05 Sep 2014 OCM
MAYCO to provide budget priorities and key projects  for the MTREF period for inclusion in the budget parameters 13 Sep 2014 CFO
Preparation of budget framework to provide parameters and request budget inputs for the 2015/16 MTREF period. 30 Sep 2014 CFO
Approval of final GDS and implementation plan 30 Sep 2014 EM
1ST quarter section 52 report for the period ending 30 September 2014 on the implementation of the budget and financial state of affairs of the municipality 22 Oct 2014 CFO/CM
One day self-assessment dialogue with EMT, MAYCO and Councillors and reviewing current implementation progress. 30 Oct 2014 EM/CM
EMT submits inputs on operational budget 03 Nov 2014 HODs
EMT to submit inputs on operational budget 14 Nov 2014 HODs
Submission of General Services Tariffs and revenue forecast. 14 Nov 2014 HODs
EMT to submit budget inputs on capital projects 21 Nov 2014 HODs
Consideration, review and inclusion of any relevant and new information. 25 Nov 2014 OCM
Initiate Cluster Based Public Participation process in line with MTREF to solicit input and comment from MMM publicson IDP thereby developing regional/cluster based plans. 25 Nov – 19 Dec 2014 DEM
  EMT Reviews and approved tentative capital budget 08 Dec2014 CM/CFO
  Budget Steering Committee (BSC) meeting to review progress on the IDP & Budget 10 Dec2014 Chairperson: BSC
 

 

STRATEGIES PHASE

Submission of the final tariffs proposal and revenue forecast.

  • Rates, Refuse Removal and Sanitation Charges
  • Water
 15 Jan 2015 GM: Revenue Man.

HOD: Engineering Services

2nd  quarter section 52 report for the period ending 31 December 2014 on the implementation of the budget and financial state of affairs of the municipality 21 Jan 2015 CFO/CM
EMT/CM reviews the first draft of the MTREF BEPP report 24 Jan 2015 HOD: Strategic Support
Centlec submit draft budget and business plans. 28 Jan 2015 CENTLEC
Submission of Mid- Year Budget and Performance Assessment Report for 2014/2015 financial year 30 Jan 2015 CFO/CM
Refining municipal Strategies, Objectives, KPA’s, KPI’s and targets so as to influence the budget. 05 Feb 2015 OCM
MAYCO Lekgotla to confirm IDP, SDBIP and Budget priorities (municipal objectives, strategies, KPIs and targets). 10 Feb 2015 EM
MMM provides Centlec with comments on draft business plan and budget. 13 Feb 2015 EM
Budget Steering Committee meeting to review progress on the IDP & Budget 13 Feb 2015 Chairperson: BSC
Centlec submit the revised draft budget and business plans 21 Feb 2015 Centlec CEO/CFO
Review tariffs and budget policies. 28 Feb 2015 CFO/HODS
PROJECT PHASE Institutional plan refined to deliver on the municipal strategy 27 Feb 2015 HOD CORPORATE SERVICES
Review and align National and Provincial allocation for inclusion in the draft IDP and MTREF budget. 27 Feb 2015 OCM
Commence with Draft MTREF budget and IDP development processes. 5 Mar 2015 CFO/CM
Directorates develop and finalise draft 2015/16 SDBIP and present to Portfolio Committees. 10 Mar 2015 HODS
One and multi-year scorecard revised and presented to MAYCO. 15 Mar 2015 OCM
INTEGRATION PHASE Horizontal and vertical alignment with, Province and other stakeholders. Integration of sector plans and institutional programmes 12 Mar 2015 OCM
Financial plan, capital investment, spatial development framework, human settlement development plan , disaster management plan, economic development strategy are developed and reviewed 13 Mar 2015 HODS
Budget Steering Committee meeting to review progress on the IDP & Budget 23 Mar 2015 Chairperson: BSC
APPROVAL PHASE

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

APPROVAL PHASE (cont)

Tabling of the Draft IDP including proposed revisions and MTREF Budget and related resolutions – MMM and Centlec. 26 Mar 2015 CFO/CM
Submission of draft IDP and MTREF to MECs Treasury and Cooperative Governance, Traditional and Human Settlements, and National. 07 Apr 2015 CFO/CM
Public participation process including hearings on Draft IDP and Budget. 07 Apr – 16 Apr 2015 DEM
IDP Budget Lekgotla. 28 Apr 2015 DEM/CM
3rd  quarter section 52 report for the period ending 31 March 2015 on the implementation of the budget and financial state of affairs of the municipality 30 Apr 2015 CFO/CM
Council meeting to deliberate and consider views of local communities and the Executive Mayor with support of MAYCO to respond to submission made during the public participation processes and IDP Budget Lekgotla 22 May 2015 EM/CM
Budget Steering Committee meeting to review progress on the IDP & Budget 28 May2015 Chairperson: BSC
Council meeting to approve IDP and MTREF budget by resolution, setting taxes and tariffs, approving changes to IDP and budget related policies, approving measurable performance objectives for revenue by source and expenditure by vote before start of budget year. 11 June 2015 EM/CM
The Executive Mayor submits the approved IDP, MTREF budget, taxes and tariffs and budget related policies to the MEC : Cooperative Governance, Traditional Affairs and Human Settlements, National and Provincial Treasury, Office of the Auditor General and makes public within 14 days after approval. 19 June 2015 CM
Publication of approved IDP and budget on the website and in local newspapers. 19 June 2015 CM
Executive Mayor approves the 2015/16 SDBIP of the City within 28 days after the approval of IDP and budget. Executive Mayor ensures that the annual performance agreements are linked to the measurable performance objectives approved with the budget and SDBIP. 10 July 2015 EM
Executive Mayor approves the 2015/16 performance agreements of the City Manager and the City Manager approves performance agreements of Heads of Department that are linked to the measurable performance objectives approved with the budget and SDBIP. 31 July 2015 EM
4th quarter section 52 report for the period ending 30 June 2015 on the implementation of the budget and financial state of affairs of the municipality 31 July 2015 CFO/CM
 Tabling of the IDP and Budget Process Plan for 2015/2016 financial year to Council.  28 Aug 2015  DEM
ADJUSTMENT BUDGET Directorate inputs into the adjustment budget. 10 Jan 2015 HODS
Council approves the adjustment budget 27 Feb 2015 EM/CM